16 projects in Telangana
Average Score
16
Total Projects
0
Completed
14
Delayed
14
Lapsed
0.0
Complaints / Project
0%
On-Time Delivery
0
Total Complaints
| Project | Score | Status | Risk | Complaints |
|---|---|---|---|---|
DNR RESIDENCY P02700003602 | 70 | Ongoing | Moderate | 0 |
SR RK REDDY RESIDENCY BLOCK P01100006485 | 70 | Ongoing | Moderate | 0 |
SR SAI REDDY ENCLAVE BLOCK P01100005049 | 66 | Lapsed | Medium | 0 |
SR SAI REDDY ENCLAVE BLOCK P01100005020 | 66 | Lapsed | Medium | 0 |
DNR ELITE P02700005489 | 66 | Lapsed | Medium | 0 |
S R T E J A R E S I D E N C P01100005999 | 66 | Lapsed | Medium | 0 |
BMR RESIDENCY P02400006020 | 66 | Lapsed | Medium | 0 |
S R S A V A R K A R R E S I D E N C P01100006174 | 66 | Lapsed | Medium | 0 |
SR RK REDDY RESIDENCY BLOCK P01100006560 | 66 | Lapsed | Medium | 0 |
DNR ELEGANCE P02700006666 | 66 | Lapsed | Medium | 0 |
SR CONSTRUCTIONS 2 P02400001427 | 60 | Lapsed | Medium | 0 |
DNR The Classe P02700004645 | 60 | Lapsed | Medium | 0 |
SR HAMPI RESIDENCY P02400006946 | 60 | Lapsed | Medium | 0 |
SR CONSTRUCTIONS P02400000587 | 59 | Lapsed | Medium | 0 |
SR CONSTRUCTIONS P02400000588 | 59 | Lapsed | Medium | 0 |
SR SAI REDDY ENCLAVE BLOCK P01100004995 | 54 | Lapsed | Medium | 0 |