5 projects in Telangana
Average Score
5
Total Projects
0
Completed
5
Delayed
5
Lapsed
0.0
Complaints / Project
0%
On-Time Delivery
0
Total Complaints
| Project | Score | Status | Risk | Complaints |
|---|---|---|---|---|
PLATINUM CITY P01400006299 | 66 | Lapsed | Medium | 0 |
DIAMOND CITY P02000005077 | 60 | Lapsed | Medium | 0 |
DIMOND CITY PHASE - P02000005391 | 60 | Lapsed | Medium | 0 |
DIAMOND CITY PHASE - P02000005856 | 60 | Lapsed | Medium | 0 |
P A R A D I S E C I T Y P H A S E - P01400006293 | 60 | Lapsed | Medium | 0 |
Builder profiles are based on publicly filed RERA data as of March 2026. Scores are informational only and not endorsed by any regulatory authority.