6 projects in Tamil Nadu
Average Score
6
Total Projects
1
Completed
5
Delayed
0
Lapsed
0.0
Complaints / Project
17%
On-Time Delivery
0
Total Complaints
| Project | Score | Status | Risk | Complaints |
|---|---|---|---|---|
Construction of Block A1, A2, A3 – 3 Blocks - Ground Floor + 3 Floors each of... TN/10/Building/0069/2020 | 80 | Completed | Low | 0 |
Construction of Block – A1, A2 of Ground Floor + 2 Floors with 96 dwelling... TN/10/Building/0062/2020 | 44 | Progress of Work as on September 2024 | High | 0 |
Construction of Residential Tenemental Blocks: Ground Floor + 3 Floors with 32... TN/17/Building/0051/2020 | 38 | Progress of Work as on June 2023 | High | 0 |
Construction of Ten Blocks in Type A, A1, A2, A3, A4, A5, A6, A7, A8, A9, A10... TN/10/Building/0063/2020 | 32 | Progress of Work as on March 2022 | High | 0 |
Construction of Type A - 20 Blocks (A1 to A20) of Ground Floor + 2 Floors of 24... TN/10/Building/0072/2020 | 32 | Progress of Work as on September 2024 | High | 0 |
Construction of Block – A1, A2, A3, A4, A5, A6, A7, A8 – Ground Floor + First... TN/10/Building/0073/2020 | 32 | Progress of Work as on September 2024 | High | 0 |