3 projects in Tamil Nadu
Average Score
3
Total Projects
1
Completed
2
Delayed
0
Lapsed
0.0
Complaints / Project
33%
On-Time Delivery
0
Total Complaints
| Project | Score | Status | Risk | Complaints |
|---|---|---|---|---|
Construction of Stilt Floor + 4 Floors with 32 tenements at 83rd Street and... TN/29/Building/0249/2020 | 80 | Completed | Low | 0 |
Construction of Ground Floor + 4 Floors with 20 Tenements (Pocket-3) comprised... TN/29/Building/0115/2021 | 38 | Progress of Work as on September 2021 | High | 0 |
Appavoo Nagar & Subbu Pillai Thottam Phase-II TN/29/Building/0287/2020 | 32 | Progress of Work as on September 2021 | High | 0 |
3 projects
Compare →4 projects
Compare →4 projects
Compare →Builder profiles are based on publicly filed RERA data as of March 2026. Scores are informational only and not endorsed by any regulatory authority.