| Project | Score | Status | Risk | Complaints |
|---|---|---|---|---|
Construction of M.S.B. Residential Flats of Type 12 of 2B + Stilt Floor + 45... TN/01/Building/0102/2017 | 85 | Completed | Low | 0 |
Stilt Floor+ 35 Floors with 175 Dwelling Units above the Common Triple Basement... TN/01/Building/0104/2017 | 85 | Completed | Low | 0 |
Construction of Stilt Floor+ 33 Floors with 264 Dwelling Units above the... TN/01/Building/0105/2017 | 85 | Completed | Low | 0 |
Gateway House TN/01/Building/0171/2023 | 85 | Completed The following Hon'ble High Court Order is hosted under Section 34(c) of the Act | Low | 0 |
Layout of House Sites TN/01/Layout/0037/2017 | 85 | Completed | Low | 0 |
Verona Block-51 TN/01/Building/0425/2021 | 60 | Progress of Work as on June 2025 The following Hon'ble High Court Order is hosted under Section 34(c) of the Act | Medium | 0 |
Octavius Building No.50 TN/01/Building/0424/2021 | 52 | Progress of Work as on June 2025 The following Hon'ble High Court Order is hosted under Section 34(c) of the Act | Medium | 0 |
Bay Haven Phase-2 TN/01/Building/0183/2023 | 52 | Progress of Work as on March 2025 The following Hon'ble High Court Order is hosted under Section 34(c) of the Act | Medium | 0 |