4 projects in Tamil Nadu
Average Score
4
Total Projects
1
Completed
0
Delayed
0
Lapsed
0.0
Complaints / Project
75%
On-Time Delivery
0
Total Complaints
| Project | Score | Status | Risk | Complaints |
|---|---|---|---|---|
Construction of Stilt Floor + 4 Floors with 11 Units in each floor totalling... TN/01/Building/0119/2017 | 85 | Completed | Low | 0 |
Construction of Ground Floor + 3 Floorswith 122 dwelling units + Shops,... TN/01/Building/0027/2018 | 85 | Completed | Low | 0 |
Construction of Ground floor + 3 floors Residential building with 16 Nos. in... TN/01/Building/0084/2018 | 85 | Completed | Low | 0 |
Sharada TN/01/Building/0075/2020 | 43 | Progress of Work as on March 2025 | High | 0 |