4 projects in Maharashtra
Average Score
4
Total Projects
0
Completed
4
Delayed
0
Lapsed
0.3
Complaints / Project
0%
On-Time Delivery
1
Total Complaints
| Project | Score | Status | Risk | Complaints |
|---|---|---|---|---|
Supreme Elysia P51800034860 | 71 | New | Low | 0 |
Supreme Elenor P51800030270 | 66 | New | Medium | 0 |
Supreme Evana P51800033931 | 66 | New | Medium | 0 |
Supreme 19 P51800000582 | 64 | Ongoing | Medium | 1 |
Builder profiles are based on publicly filed RERA data as of March 2026. Scores are informational only and not endorsed by any regulatory authority.