6 projects in Maharashtra
Average Score
6
Total Projects
0
Completed
2
Delayed
0
Lapsed
0.0
Complaints / Project
0%
On-Time Delivery
0
Total Complaints
| Project | Score | Status | Risk | Complaints |
|---|---|---|---|---|
ISLE OF CALM TOWER 1 P51800077922 | 76 | New | Low | 0 |
ISLE OF CALM TOWER 2 P51800077401 | 75 | New | Low | 0 |
PARIJATAK CO OP HSG SOC LTD P51800001974 | 64 | Ongoing | Medium | 0 |
MUTUAL BENEFIT CO OP HSG SOC LTD P51800002333 | 64 | Ongoing | Medium | 0 |
Mulund Om CHS Ltd P51800022406 | 64 | New | Medium | 0 |
WOODLAND MULUND CHS LTD P51800034164 | 56 | New | Medium | 0 |
Builder profiles are based on publicly filed RERA data as of March 2026. Scores are informational only and not endorsed by any regulatory authority.