5 projects in Maharashtra
Average Score
5
Total Projects
0
Completed
0
Delayed
0
Lapsed
11.6
Complaints / Project
0%
On-Time Delivery
58
Total Complaints
| Project | Score | Status | Risk | Complaints |
|---|---|---|---|---|
Andheri Sahkar Co-operative Housing Society Ltd. P51800008368 | 60 | Ongoing | Medium | 0 |
D N Nagar Suryakiran CHS Limited P51800007876 | 56 | Ongoing | Medium | 16 |
D N Nagar Jai Bhavani CHS Ltd P51800008223 | 52 | Ongoing | Medium | 4 |
D N Nagar Krishna CHS Ltd P51800007005 | 51 | Ongoing | Medium | 15 |
D N Nagar Shivneri CHS Ltd P51800004197 | 45 | Ongoing | Medium | 23 |
Builder profiles are based on publicly filed RERA data as of March 2026. Scores are informational only and not endorsed by any regulatory authority.