10 projects in Maharashtra
Average Score
10
Total Projects
0
Completed
2
Delayed
0
Lapsed
0.0
Complaints / Project
0%
On-Time Delivery
0
Total Complaints
| Project | Score | Status | Risk | Complaints |
|---|---|---|---|---|
ROSHAN MILESTONE WING B P52100033170 | 86 | New | Low | 0 |
ROSHAN MILESTONE WING C P52100033798 | 86 | New | Low | 0 |
ROSHAN MILESTONE WING A P52100033143 | 86 | New | Low | 0 |
ROSHAN MILESTONE WING H P52100051615 | 86 | New | Low | 0 |
ROSHAN MILESTONE WING D P52100034573 | 86 | New | Low | 0 |
ROSHAN MILESTONE WING E P52100050418 | 86 | New | Low | 0 |
ROSHAN MILESTONE WING F P52100050918 | 74 | New | Low | 0 |
ROSHAN MILESTONE WING G P52100051473 | 74 | New | Low | 0 |
ROSHAN ONE WING B P52100004526 | 56 | Ongoing | Medium | 0 |
ROSHAN ONE WING C P52100006758 | 56 | Ongoing | Medium | 0 |
Builder profiles are based on publicly filed RERA data as of March 2026. Scores are informational only and not endorsed by any regulatory authority.