8 projects in Maharashtra
Average Score
8
Total Projects
0
Completed
7
Delayed
0
Lapsed
7.6
Complaints / Project
0%
On-Time Delivery
61
Total Complaints
| Project | Score | Status | Risk | Complaints |
|---|---|---|---|---|
EKTA CREST P51800046149 | 80 | New | Low | 0 |
EKTA TRINITY P51800005021 | 71 | Ongoing | Low | 0 |
EKTA MAPLEWOOD P51800001523 | 66 | Ongoing | Medium | 0 |
EKTA GREENVILLE PHASE 1 WING I AND J P51600001224 | 64 | Ongoing | Medium | 1 |
EKTA GREENVILLE PHASE 3 P51600001510 | 60 | Ongoing | Medium | 3 |
BROOKLYN PARK PHASE IV P99000000417 | 57 | Ongoing | Medium | 49 |
EKTA GREENVILLE PHASE 2 WING O , P , Q AND R P51600000685 | 57 | Ongoing | Medium | 8 |
FLORIDA P52100015426 | 57 | New | Medium | 0 |